Construction of Sptic Tank Pound and Pump House for Sewerage System.
Special Repair Of P/F Angle lron Frame At Residential colony Guddu
Providing of False ceiling and wall Treatment of Multi purpose hall of officers club.
Construction Of Approaches to 09 NOS Tube Wells at Taliri Canal Muzaffargarh.
Supplying and Laying of PVC Tiles Sheet on the Approaches of Turbine Hall.
Renovation of R.O office Building including cost of shed at Shalamar Lahore.
lmprovement of Area Between Unit NO.1 To 8 At GTPS Faisalabad.
Construction of Equipment Foundations Cable Trenches & Switch Yard Fencing for Ext. of 4 Nos. 220 Kv Bays at TPS M.Garh.
Supply Of Material Ball Bearings At Muzaffar Garh.
Rcc Approach Road About I KM Around Decanting Station at TPS M.Garh Work Done in Association with M/S Ali fgg. Company.
Construction of Plate form for Oil Tanks at Decanting Channel TPS Guddu.
Laying Acid Resistant Tiles ln Acid Resistant Material in Water Treatment Plant at Muzaffar Garh.

Construction of Boundary Wall at 500
Special Repair of overhead Water At Shahdara Power Station LAHORE.
Construction of Store building at CMTL Lahore.
CONSTRUCTION OF SDO OFFICE AT WARBURTEN
Special Repair of FF Type Quarters at SPS Faisalabad.
Construction of XEN / RO Office & pro Water supply and sewerage arrangement at OKARA.
Construction of Electrical Equipment Foundation, Cable Trenches Transformer Extension in 11 KV Room at KhUDIAN
Construction of Double Story building at Gulberg Lahore.
Construction of single story house at Johar Town Lahore.
Construction of 132 KV Grid Station Shahamar-II Lahore.
Construction of remaining Boundry Wall At 132 KV Grid Station Shalamar-ll Lahore
Construction of Capasture bay At 132 KV Grid Station Sailkot CANNT
Construction of XEN/RO office at Kot Addou
Construction of SDO office at Multan
Construction of Double story house at Model town lahore
Construction of Transformer Bay at Daska.
Constructoin of Transformer Bay AT Shalamar ll Lahore.
A&MR of 132 KV Grid Garden TOWN LAHORE.
A&MR of 132 KV Grid TOWN ShiP LAHORE.
A&MR of 132 KV Grid IQBAL TOWN LAHORE.
A&MR AT XENIRO OFFICE TOWN SHIP LAHORE.
Supply & sPreading water borne Gravel at Sarfraz Nager Bahi Pharoo.
Supply & Tranch cover at 500 KV Grid Sabzazar Lahore.
Construction of 132 Kv grid station at BODUMALHI.
CONSTRUCTION OF 1ST Floor / Hall,Store Room Quality Room ELCTRIFICAT DANIAL NETWARE Lahore

Ranovation of house 30-D Valenchia
Strengthening Of Columns Of l/Arrestors Braker, CT/PT and lsolstor At 132 Kv Grid Station Pattoki.
RE-Construction of Boundry Wall Around Power House And Colony Area At GTPS Faisalabad.
RE-Construction of Boundry Wall At 66 Kv Grid Station Shadun Lund.
RE-Construction of Boundry Wall At 132 Kv Grid Station Vehari Road Multan.
Construction of Electrical Equipment Foundation, Cable Trenches Transformer Extension in 11 KV Room a1132 Kv Grid Vehari Road Multan.
Construction of Electrical Equipment Foundation, Cable Trenches Transformer Extension in 11 KV Room at 132 Kv Grid Station Khanewal Road Multan.
Construction of 2 No D Type Residence At MEPCO H.Q. Multan
Construction of Under Ground Dirty Oil Storage Tank 10000 Gallons Capacty At M&T Work Shop Qasim Pur Multan.
Renovation Under AM&R Of Residential Building At MPCO H.Q Multan.
Renovation UnderAM&R Of NON Residential Building At MPCO H.Q Multan
Renovation Under AM&R Of NON Residential Building At MPCO H.Q Multan
Construction of Rataning/Boundary WallAt 132 Kv grid Station Sheikhupura.
Renovation Of Boundary Wall Barbed Waire At 132 Kv Grid Station Bhikhi.
Water Supply At 132 Kv Grid Station Sheikhupura.
Extention in Yard Fence Raising of Boundary Wall lnstallation of injector Pump & Maintenance of control House Building At 132 Kv Grid P.W.R Lahore.
lffiprovement of Non Residential Building RE-Construction of Boundry Wall At 132 Kv Grid Gulstion-E-Ravi Lahore.
lmprovement of132 Kv Grid Station Quartaba Lahore.
Raising Of Boundry WallAnd P/F Barbed Waire 7 Rows At Punjmehal Lesco Head Quarter Lahore.
CONSTRUCTION OF BMall at 500 kv Grid station Gatti Faisalabad
Construction of 4th T bay at johr town grid lahore.
A&MR of residentiol building at 5oo Kv grid station Multan.
Construction of 11 KV Trench At 132 K grid station joahr town lahore.
PROVIDING GMVEL in Yard at 132 KV grid station joahr town lahore.
Construction of 1 no E type Qurter at 1 kv grid station joahr town lahore.

Construction of 1 no additionol room at 132 kv grid station joahr town lahore
A&MR 12 nos cat-v Flats at 132 kv grid station joahr town lahore
A&MR 2 NOS C type at 132 kv grid station joahr town lahore
A&MR 4 NOS CAT lV flats at 132 kv grid station joahr town lahore
A&MR 2 NOS CAT 2(B) type at 132 kv grid station joahr town lahore
Supply & Fixing G.l Plate Form at 220/132 Kv Grid station Muzaffar gahr nev
Construction 3rd t bay and extention of 11 kv room at 132 kv grid shamkey.
Boundrey Wallat 132 KV Grid Station Muredky (_portion 1)
Construction of 2 Nos line Bay at 132 KV grid Sadiqabad.
Water Supply Sistem At 132 KV grid VEHARI ROAD MULTAN
Water Supply Sistem At 132 KV grid KHANWAL ROAD MULTAN.
Water Supply Sistem At 132 KV grid MUKDOM RASHID MULTAN
Water Supply Sistem At 132 KV grid INDESTRIAL STATE MULTAN.
Construction of 1 no line bay at 132 KV grid station KOTADDU

RE Surfecing of Roads AT NGPS MULTAN.
A&MR MEPCO H.Q MULTAN.
Construction Of SDO office AT 132 KV GRID Station (NEW) SAHIWAL
Instalation OF Fiber Glass Roof /Caber at 132 l$/ GRID Station old SAHIWAL
Construction of4 nos D type Flats at 132 KV GRID STATION OLD SAHIWAL.
Boundrey Wall at 132 KV Grid Station Muredky (-portion 2
WATCH TOWER AND SECURITY ROOM AT MUREDEKY.
WATER SUPPLY AT 1321 KV GRID STATION LAYYAH.
WATER SUPPLY AT 66 KV GRID STATION KAROR.
CONSTRUCTION OF BOUNDRY WALL AT MUZAFFAR GARH
LAYING OF FLOORS AT POWER HOUSE AREA AT SPS FAISALABAD
LAYING OF FLOORS OF BASKET ball & lawn Tense court in SchoolAt SPS FAISAIABAD
Special Repair of 30 Nos F type qurte At FESCO FATSALABAD
CONSTRUCTION OF ELECTRICAL EQIEPMENT FOUNDATION AND EXTENTION OF SWITCH YARD AT 66 KV GRID STATIoN BASIRPUR.

4 Months   PD Phase-I TPS Muzaffargarh
4 Months   C.E TPS Guddu.
2 Months   P.D Phase-l TPS M.Garh
4 Months   P.D Phase-2 TPS M.Garh
3 Months  RE Phase-2 Unit 5&6 TPS Muzaffar Garh.
3 Months   C.E CivilT&G Lahore.
3 Months  R.E GAS Turbine Power Station Faislabad
9 Months   Project Director GSC Multan.
2 Months   R.E Unit 5&6 TPS M.Garh.
6 Months   R.E I TPS Muzaffar Garh.
4 Months   C.E Thermal Power Station Guddu.
3 Months   R.E-I TPS Muzaffar Garh.

2 Months   XEN CIVIL NTDC Lahore
1 Month   RE GTPS FAISALABAD
2 Months   PD HYDROLGY LHR
3 Months   XEN CIVIL LESCO
6 Months   RS SPS FAISALABAD
6 Months   XEN CIVIL LESCO
3 Months   XEN TLC NTD Lahore.
6 Months   Private
4 Months   Private
6 Months   PD GSC LAHORE.
1 Month   XEN GC IAHORE.
2 Months   XEN TLC NTD Lahore
6 Months   PD GSC MULTAN.
3 Months   PD GSC MULTAN.
6 Months   Private
2 Months   XEN TLC NTDC LHR,
3 Months   XEN GC NTDC LHR.
1 Month   XEN CIVIL LESCO.
1 Month   XEN CIVIL LESCO.
1 Month   XEN CIVIL LESCO.
1 Month   XEN CIVIL LESCO.
2 Months   XEN CIVIL NTDC LHR.
2 Months   XEN CIVIL NTDC LHR.
6 Months   XEN CIVIL NTDC LHR.
6 Months   Private

1 Months Private
15 Days XEN CIVIL LESCO.
9 Months RE GTPS FAISALABAD
6 Months Manager GSO MEPCO.
2 Months Manager GSO MEPCO.
3 Months PD GSC Multan

4 Months PD GSC Multan

9 Months By. Manager Civil MEPCO
6 Months By. Manager Civil MEPCO
6 Months By. Manager Civil MEPCO
4 Months By. Manager Civil MEPCO
4 Months By. Manager Civil MEPCO
6 Months XEN CIVIL LESCO.
1 Months XEN CIVIL LESCO.
1 Months XEN CIVIL LESCO.
2 Months XEN CIVIL LESCO.

1 Months XEN CIVIL LESCO.
1 Months XEN CIVIL LESCO.
1 Months XEN CIVIL LESCO.
1 Month XEN CIVIL EVH LAHORE
2 Months P.D GSC LESCO
2 Months XEN CIVIL GSO NTDC MULTAN.
1 Months BY.MANAGER CIVIL LESCO
1 Months BY.MANAGER CIVIL LESCO
3 Months BY.MANAGER CIVIL LESCO

1 Month BY.MANAGER CIVIL LESCO
1 Month BY.MANAGER CIVIL LESCO
1 Month BY.MANAGER CIVIL LESCO
1 Month BY.MANAGER CIVIL LESCO
1 Month BY.MANAGER CIVIL LESCO
25 days Xen TL EHV NTDC Faisalabad
2 Months PD GSC LESCO
1 Months PD GSC LESCO
45 Days XEN EHV CONSTRUCTION LAHORE
2 Months XEN SS&T MEPCO
2 Months XEN SS&T MEPCO
2 Months XEN SS&T MEPCO
2 Months XEN SS&T MEPCO
2 Months XEN GC MEPCO

3 Months RE NGPS MULTAN
5 Months XEN CIVIL MEPCO
12 Months XEN CIVIL MEPCO
6 Months XEN CIVIL MEPCO
12 Months XEN CIVIL MEPCO
3 Months PD GSC LESCO
2 Months PD GSC LESCO
2 Months XEN SS&T MEPCO.
2 Months XEN SS&T MEPCO.
5 Months XEN CIVIL EHV LAHORE.
3 Months RE SPS FAISALABAD
3 Months RE SPS FAISALABAD
3 Months BY Manager Civil FESCO
2 Months PD GSC LESCO